Tasks with prerequisites, such as courses, build steps or package installs, need an order in which every task comes after everything it depends on. That's a topological order of a directed graph, and one exists exactly when the graph has no cycle. Usually there are many valid orders, so the problem has to say which one it wants. This skill covers Kahn's algorithm, how ties are broken, and the round-by-round version that counts semesters.
We'll go from simple to more technical:
- The pattern: Kahn's algorithm, taking ready tasks from a min-heap.
- A second flavor: rounds, where each round takes everything ready at once.
- Where topological order runs in production (builds, installs, schedulers).
- What breaks it: tie rules, a short result, and rounds that merge.
The approach
Java
List<Integer> topoSort(int n, List<List<Integer>> adj) {
int[] indegree = new int[n];
for (List<Integer> next : adj) for (int v : next) indegree[v]++;
PriorityQueue<Integer> ready = new PriorityQueue<>(); // min-heap: smallest ready node first
for (int v = 0; v < n; v++) if (indegree[v] == 0) ready.add(v);
List<Integer> order = new ArrayList<>();
while (!ready.isEmpty()) {
int node = ready.poll();
order.add(node);
for (int next : adj.get(node)) {
if (--indegree[next] == 0) ready.add(next); // its last prerequisite just finished
}
}
return order; // shorter than n means there was a cycle
}
Python
import heapq
def topo_sort(n: int, adj: list[list[int]]) -> list[int]:
indegree = [0] * n
for targets in adj:
for v in targets:
indegree[v] += 1
ready = [v for v in range(n) if indegree[v] == 0]
heapq.heapify(ready) # min-heap: smallest ready node first
order = []
while ready:
node = heapq.heappop(ready)
order.append(node)
for nxt in adj[node]:
indegree[nxt] -= 1
if indegree[nxt] == 0: # its last prerequisite just finished
heapq.heappush(ready, nxt)
return order # shorter than n means there was a cycle
Kahn's algorithm keeps a pool of "ready" nodes - in-degree zero, nothing left to wait for. Taking one removes its outgoing edges, which may make others ready. Any node taken has had all its prerequisites taken before it, so the order is valid. The pool's type decides which valid order: a min-heap always takes the smallest ready node, which produces the unique lexicographically smallest order. On 5->2, 5->0, 4->0, 4->1, 2->3, 3->1 the heap gives 4 5 0 2 3 1; a plain FIFO queue gives 4 5 2 0 3 1 - also valid, just different.
A second flavor: rounds instead of a list
Process the ready pool in rounds - everything ready now, then everything that became ready because of them - and the number of rounds is the minimum number of "semesters" needed if any number of independent tasks can run in parallel:
Java
int rounds = 0, taken = 0;
while (!ready.isEmpty()) {
rounds++;
int size = ready.size(); // snapshot: only what's ready at the start of this round
for (int i = 0; i < size; i++) {
int u = ready.poll();
taken++;
for (int v : adj.get(u)) if (--indegree[v] == 0) ready.add(v);
}
}
return taken == n ? rounds : -1; // -1: a cycle - some tasks can never start
Python
rounds = taken = 0
while ready:
rounds += 1
for _ in range(len(ready)): # range() reads the size once: only what's ready now
u = ready.popleft()
taken += 1
for v in adj[u]:
indegree[v] -= 1
if indegree[v] == 0:
ready.append(v)
result = rounds if taken == n else -1 # -1: a cycle - some tasks can never start
The round count equals the number of nodes on the longest dependency chain. It's the same level-by-level BFS shape as tree level order, including its classic bug: re-reading ready.size() in the loop condition lets newly ready nodes slip into the current round. (In Python, for _ in range(len(ready)) reads the size once; an inner while ready: has the bug.)
Where you'll see it
Build systems, package managers, database migration runners, spreadsheet recalculation and task schedulers all compute a topological order of their dependency graph first. The round-by-round version is how schedulers find the critical path - the minimum number of stages when independent jobs run in parallel. A fixed tie-break (like the min-heap) makes the order independent of how inputs happened to be listed, which matters for reproducible builds.
Which tool for which job?
| You need | Use |
|---|---|
| Any valid order | Kahn's algorithm with a FIFO queue |
| The lexicographically smallest order | Kahn's algorithm with a min-heap |
| The number of rounds (semesters, parallel stages) | Kahn's algorithm level by level: the longest path |
| An order with no in-degree array | DFS reverse postorder |
| Cycle detection at the same time | check order.size() == n |
| Python, built in | graphlib.TopologicalSorter |
Common mistakes
| Mistake | What happens | Do this instead |
|---|---|---|
| Expecting FIFO to give the smallest order | [2, 3, 0, 1] instead of [2, 0, 3, 1] | a min-heap when the order is specified |
| Ignoring a short result | tasks on a cycle silently disappear | check the length equals n |
| Re-reading the queue size within a round | rounds merge and get undercounted | snapshot the size first |
| DFS ordering on a deep chain | stack overflow | Kahn's algorithm, or an iterative DFS |
Check yourself
Try to answer before opening each one - recalling beats re-reading.
1. Kahn's algorithm with a FIFO queue is run twice on the same input. Can the outputs differ?
Show answer
No - it's deterministic. But its order depends on the order nodes and edges were listed, and it's often not the lexicographically smallest: on the lesson's example FIFO gives 4 5 2 0 3 1 while the min-heap gives 4 5 0 2 3 1. Both are valid.
2. The topological sort returns 4 nodes for a 6-node graph. What happened?
Show answer
The graph has a cycle. Nodes on a cycle (and any node that depends on one) never reach in-degree zero, so they're never taken. A result shorter than n is Kahn's way of saying "not a DAG".
3. Why does processing Kahn's algorithm in rounds give the minimum number of semesters?
Show answer
Round k takes every course whose prerequisites were all finished in earlier rounds - nothing can be taken sooner. The number of rounds equals the length (in nodes) of the longest prerequisite chain, and no schedule can beat that chain, since each course on it must wait for the one before.
Key takeaways
- A topological order exists exactly when the directed graph has no cycle.
- Kahn's algorithm repeatedly takes a node with no remaining prerequisites; a result shorter than n means a cycle.
- The ready pool's type picks the order: a min-heap gives the lexicographically smallest (O(V log V + E)); a FIFO queue is deterministic but input-order dependent (O(V + E)).
- Processing in rounds (with a size snapshot) counts the minimum number of parallel stages - the longest dependency chain.
- DFS finish order, reversed, is also a topological order.